Amendment No. 1 to Master Circular on ‘Gati Shakti Multi-modal Cargo Terminal (GCT)/2022/0 dated 06.12.2022’

Freight Marketing Circular No. 05 of 2024 · 2024-02-04
Circularfreight

Open the official PDF on indianrailways.gov.in

Circular numberFreight Marketing Circular No. 05 of 2024
File numberNo. 2021/TC(FM)/18/23
Date2024-02-04
TypeRates Master Circular
Topicfreight
DirectorateTraffic Commercial (Freight Marketing)
Official PDFindianrailways.gov.in

Summary

Amendment No. 1 to Master Circular on ‘Gati Shakti Multi-modal Cargo Terminal (GCT)/2022/0 dated 06.12.2022’ percentage of Terminal Charges and | share of Terminal Charge/Terminal Access

Text of the circular

Freight Marketing
Circular No. 05 of 2024

भारत सरकार GOVERNMENT OF INDIA
रेल मंत्रालय MINISTRY OF RAILWAYS

(रेलवे बोर्ड RAILWAY BOARD)

; रेल भवन, नई feeeit-110001
No. 2021/TC(FM)/18/23 (Pt-2) Rail Bhavan, New Delhi-110001, dated|4.02.2024
The General Managers.
1. Central Railway, CSMT, Mumbai 9. North Western Railway, Jaipur
2. Eastern Railway, Fairlie Place, Kolkata 10. Southern Railway, Chennai
3. East Central Railway, Hajipur 11. South Central Railway, Secunderabad
4. East Coast Railway, Bhubaneshwar 12. South Eastern Railway, Garden Reach, Kolkata
5. Northern Railway, New Delhi 13. South East Central Railway, Bilaspur
6. North Central Railway, Prayagraj 14. South Western Railway, Hubli
7. North Eastern Railway,Gorakhpur _—_‘15. Western Railway, Churchgate, Mumbai
8. Northeast Frontier Railway, Maligaon 16. West Central Railway, Jabalpur

Managing Director,
DFCCIL, New Delhi.

Chairman & Managing Director,
KRCL, Navi Mumbai.

Sub: Amendment No. 1 to Master Circular on ‘Gati Shakti Multi-modal Cargo
Terminal (GCT)/2022/0 dated 06.12.2022’.

Ref: Master Circular on GCT/2022/0 issued vide Board’s letter No.
2021/TC(FM)/18/23 dated 06.12.2022.
KARR KEK
The policy guidelines on “Gati Shakti Multi Modal Cargo Terminal (GCT)’ were issued to
Zonal Railways vide FM Master Circular/GCT/2021 under Board’s letter No.
2021/TC(FM)/18/23 dated 06.12.2022.

Z: Board is in receipt of various suggestions with respect to the provisions of GCT Master
Circular 2022, which have been examined in this office and accordingly it has been decided to

amend/insert following paras in this Policy.

Amended/ Inserted paras in GCT Master Circular 2022 :

Existing para to be modified
Para 5.1.1 of GCT Main Policy -

Para 5.1.1 of GCT Main Policy

As per GCT policy para no. 5.1.1 "for the
connectivity portion of GCT through the
Railway land, including the land to be
acquired by Railway for this purpose

As per GCT policy para no. 5.1.1 "for the
connectivity portion of GCT through the Railway
land, including the land to be acquired by
Railway for this purpose under para 17.2 of this

fage hia. ०4

Freight Marketing
Circular No. 05 of 2024

Existing para to be modified

Amended/ Inserted para

under para 17.2 of this policy, only the

minimum essential infrastructure of
track (including bridges and earth work,
as required), OHE and_ signalling

equipment shall be provided at the cost
of GCTO (other assets not related to
track, signalling, or OHE, if required,
shall be constructed by Railway at its
own cost). In case of any dispute, the
decision of DRM shall be final in this

regard.
Para no. 5.5.2.2 of Main Policy

“The repayment of Capital cost will be
done only if the Terminal achieves the
target of loading one Million Tonne per
annum within 2 calendar years of

commissioning”.

years of commissioning.

policy, only the minimum essential infrastructure
of track (including bridges and earth work, as
required), OHE and S&T equipment-which are
essential requirement for operation of train
movement, shall be provided at the cost of GCTO
(other assets not related to track, signalling, or
OHE, if required, shall be constructed by Railway
at its own cost). In case of any dispute, the
decision of DRM shall be final in this regard.

Para no. 5.5.2.2 of Main Policy

“The repayment of Capital cost will be done only
if the Terminal achieves the target of Freight

handling (inward 25 well as outward) of one

Million Tonne per annum within two calendar

Para 17.3 of Main Policy

— “Unless otherwise mentioned in this
policy, all ‘Commercial and operating
rules’ as applicable for a goods-shed for
booking, supply and delivery of goods
shall be applicable at GCTs".

Para 5 of Schedule-I of Policy

"Within four (04) weeks of receipts of
IPA, the applicant will submit details of
the project along with Engineering Scale
Plan (ESP) of the serving station/new
Block Hut/Block Station to the DRM”.

Para 17.3 of Main Policy

“Unless otherwise mentioned in this policy,