Guidelines for provision of minimum infrastructure while developing new GCTs in order to reduce the cost of terminal

FM Circular No. 21 of 2024 · 2024-09-03
Study materialfreight

No official Railway Board PDF has been traced for this entry yet. The text below was read from the document held in the library.

Circular numberFM Circular No. 21 of 2024
File numberNo EI/distributed
Date2024-09-03
TypeFreight Marketing Circular
Topicfreight

Summary

Guidelines for provision of minimum infrastructure while developing new GCTs in order to reduce the cost of terminal Chairman & CEO, Member (O&BD), Member (Financ~), Member (Infra.), Member (T&RS),

Text of the circular

FM Circular No. 21 of 2024 
~ F(d ft <cfil < GOVERNMENT OF INDIA 
~ 
1-t?i1~4 MINISTRY OF RAILWAYS 
(m~ RAILWAYBOARD) 
No. 2022ffC(FM)/18/07-Part 2 
B~ ,3:tRRil -110001 
Rail Bhavan, New Delhi-110 001, dated 03.09.2024 
General Managers, 
All Indian Railways 
Sub:-
Guidelines for provision of minimum infrastructure while developing new GCTs in 
order to reduce the cost of terminal. 
******* 
The Gati Shakti Cargo Terminal (GCT) policy was launched in 2021 to encourage private sector 
participation in developing freight terminals and integrating modem technology in freight management. • 
While the objective to rationalize the capital cost of GCT, Board (MI, M/T&RS and Member/O&BD) has 
issued the following guidelines for consideration: 
(1) Civil Engineering Standards -
a. Rails: 52 kg/m (second hand) or 52 Kg/m (Industrial Use), Sleeper density of 1540/km and 
Ballast Depth of 300 mm may be considered with maximum permissible speed up to 50 kmph as 
' per extant provision of IRPWM for loads other than 25T and CC+8+ 2. 
• 
b. If the TVU is lesser than 20000, a decision to provide LC may be taken as per the site condition 
considering the capitalized cost of maintenance of a manned LC gate. 
(2) OHE Standards -
a. Conventional OHE may be planned on lead portion and inside GCT. 
b. Circuit breakers may be planned for GCT to isolate the terminal from mainline. 
c. Instead of the masts, portals may be planned in the terminal yard wherever possible to reduce the 
• land acquisition cost. 
d. No TSS, SSP/ SP to be planned on siding account. However, if it becomes necessary to provide 
TSS (to meet load on account of extra traffic\ the same may be planned at the Railway's cost. 
(3) S&T Standards-
a. No EI/distributed EI and track circuiting to be insisted in the siding/terminal or its R&D yard. 
The yards may be non-interlocked with hand operated points. 
(4) Depending upon the quantum of traffic ~d distance of the siding from station, if the 
facilities· such as El, TSS, auto signalling etc. are required, it should be planned w • the 
personal approval of GM on the recommendation of PCOM. 
This issues with the approval of Board (Ml, Memper/f &RS, Member/O&BD) 
(As • 
·1ayan) 
Dy. Director/ FM (Strategy) 
Railway Board

FM Circular No. 21 of 2024
I 
I 
No. 2022ffC(FM)/18/07 .- Part 2 
Rail Bhavan, New Delhi-110001, ~ated 03.09.2024. 
1. The Principal Chief Operations Managers, All Indian Railways. 
2. The Principal Chief Commercial Managers, ~l fudian,Railway~ (except~). 
3. The Chief Traffic 'Planning Managers, All Indian Ratlwa~s. 
' 
4. The Principal Chief Electrical Engineers, All Indian Railways .• , 
5. The Principal Chief Engineers, All Indi<W R~lways. ,, 
' 
6. The Chief Commercial _Managers (FM), All Indian Railways, . : 
' 
I 
7. Director General, ROSO, Manak Nagar, Lucknow. 
'· ' 
, 
\ 
' 
8. Director, Indian Railways Institute of Transport Management (IRITM), Lucknow. 
9. Director General~ National Academy 'of Indian Railways, VaJioqara., 
/ 
I 
,1,t 
10. The Managing Dir~ctor/Chief Commercial :ry.t:anag~r,, ~op;kaq., ~a~way • C<i>rporation Ltd., Bela ur 
Bhawan, Plot No. 6, Sector-11, CBD Belapur~. Navi Mumbai~ 4,000'14. 
,,. 
11. Managing Director, CRIS, Chanakyapuri, Ne~ Natiohal Rail Museum, ~ew Delhi. 
12. Managing Director, DFCCIL, Pragati Maidan, New Del~t ",, 
• 
; '• 
. • 
No. 2022/fC(FM)/18/07 - Part 2 
I 
I 
I ' 
II 
'l11 
,, 
•I 
I 
'I 
I 
'I 
I 
' 
I 
' 
,. 
I 
• 
,, 
• 
', I 
I• 
' 
" 
' 
1' 
I 
I 
I 
·•j 
I 
,l 
, 
(As--~- Uj ayan) 
,,Dy. Director/ FM (St ategy) 
Rail Bha~an, New Delhi-110001, ~ted 03.09.2024 ·1 
I 
. 
I 
I• 
•I' 
I 
\ 
I 
I 
, 
I 
,1 
' 
Copy for kind information to: 
•• 
. 
1. Chairman & CEO, Member (O&BD), Member (Financ~), Member (Infra.), Member (T&RS), 
DG(RPF), and Secretary Railway Board, New Dt:;)hi. 
. 
l 
,, 
, 
2. AM{Traffic), AM(C), 
Adv (Infra), Adv. (Vig.), EDTC(Rat~s), EDTT(M), EDTT(S), 
EDTT(F), ED(Plg.) EDT(PPP), EDV(T), EDF(C), DTT(Coord), OSD/Chairman & CEO, 
OSD/Member 

Extract shown above; the full text is available in the search app.