Loading of Granite Blocks in Wagons

No.MW/LOADING · 2024-07-05
Circularfreight

No official Railway Board PDF has been traced for this entry yet. The text below was read from the document held in the library.

Circular numberNo.MW/LOADING
Date2024-07-05
TypeCommercial Circular
Topicfreight

Summary

Loading of Granite Blocks in Wagons A proper system shall also be put in place to ensure that loading and securing by

Text of the circular

Hkkjr ljdkj & jsy ea=ky; 
vuqla/kku vfHkdYi vkSj ekud laxBu 
y[kuÅ & 226011 
EPBX (0522) 2451200 
Fax    (0522) 2458500 
Government of India - Ministry of Railways 
Research Designs & Standards Organisation  
Lucknow – 226011 
DID (0522) 2450115 
DID (0522) 2465310 
 
 
 
No.MW/LOADING & SECURING                                                                      Date: 05.07.2024 
 
CRSE/Frt, 
Mechanical HQ office 
SWR, Gadag Road, 
Hubli - 580020 
 
Sub:  Loading of Granite Blocks in Wagons    
          Ref: (i) CRSE/SWR letter no. SWR/M/N/19/Vol-XII dated 20.06.2024 
                  (ii) Railway board letter no. 2019/M(N)/204/6 (E:3324111) dated 7.05.2024 
****** 
        
1. Vide ref. (ii) above; loading diagram for loading of 04 Granite Blocks on a wagon 
was given as per the requirements submitted at that time.  
2. Now the proposal for loading of 06 no’s to 15 no’s of granite block has been 
submitted vide ref.(i) above but it may be noted that no dimensions of these blocks 
have been mentioned in the submitted proposal. In the absence of complete 
dimensions, standard loading diagrams could not be made. However, an envelope 
loading diagram no. SK-WD-III-02/2024 Alt-Nil with the general guideline to be 
followed has been prepared and is attached herewith. 
3. This envelope drawing has been prepared to meet varied requirement of granite 
loading in open wagons (BOXN, BOXNR and BOST) by Zonal Railway.  South 
Western Railway with experience of loading such consignments since 2008 will 
ensure that additional measures are also taken to ensure safety and to avoid 
damages to the wagons.  
4. A proper system shall also be put in place to ensure that loading and securing by 
loading firm is done following guidelines issued by Zonal Railway and system for 
certification of the same is also put in place. 
A feedback shall be sent by Zonal Railway to RDSO after 06 months to incorporate 
any changes/improvements required in above loading arrangement.   
 
       Encl.: As above   
 
 
                                                                                         
                                                                                                           (Sanjay Kumar) 
 
 
 
 
 
 
 
 
            Director Stds./Wagon 
 
 
 
 
 
 
 
 
        For Director General/Wagon      
 
 
File No.RDSO-MW0GENL(EOFC)/8/2023-O/o PED/SW/RDSO

File No.RDSO-MW0GENL(EOFC)/8/2023-O/o PED/SW/RDSO

Related circulars

Search the whole library

Open this circular in the search app · Search all 4,025 documents