IR’s Plan for “Mission 3000MT” Originating Freight

No.2022/Infra/17/5 · 2022-04-30
Currency not verifiedCircularfreight
Currency not verified. Nobody has confirmed whether this circular is still in force. Check the present position before relying on it. The official Railway Board PDF always prevails over anything shown here.

No official Railway Board PDF has been traced for this entry yet. The text below was read from the document held in the library.

Circular numberNo.2022/Infra/17/5
Date2022-04-30
TypeCommercial Circular
Topicfreight
CurrencyCurrency not verified

Summary

lines/GC/Yard remodelling works/2x25kv works/25T upgradation /long

Text of the circular

भारत सरकार
रेल मंत्रालय, (रिलवे बोर्ड)

R.N. SINGH af रेल भवन, नई दिल्‍ली-110001
सचिव रेलवे बोर्ड Ge GOVERNMENT OF INDIA
Secretary, Railway Board waa aaa MINISTRY OF RAILWAYS

ही y (RAILWAY BOARD)
RAIL BHAVAN, NEW DELHI-110001
Ceo)
स्वच्छ
एक कदम स्वच्छता की ओर
0.0. No.2022/Infra/17/5 Dated : 30-04-2022

Dear Shri Jain

Sub. : IR’s Plan for “Mission 3000MT” Originating Freight.
Ref. : Railway Board’s Order No.ERB-I/2022/23/30 dated 28-04-2022.

Ministry of Railways (Railway Board) has constituted a Multi-Disciplinary
Committee to deliberate and submit their recommendations/action plan to achieve
ambitious target of freight loading of 3000 MT per annum by 2027 by undertaking
enabling measures like augmentation/upgradation of network, signalling & traction
system to enhance capacity and proliferating /upgrading rolling stock etc. The committee
has to submit recommendations within 10 days.

2. General Managers are requested to consult all internal & external stakeholders
and submit their inputs on the following areas for their respective Zonal Railway :-

(1) Capacity Enhancement works required for achieving 3 times the present
loading in Zonal Railway in terms of new lines/doublings/34-4th
lines/GC/Yard remodelling works/2x25kv works/25T upgradation /long
haul operation/traffic facility works/terminal improvement works/de-
bottlenecking works etc. alongwith target date for their completion. For this
purpose, works can be divided into :-

(a) Already sanction works; &
(b) New Works required to be sanctioned.
(ii) Strategy for inducing modal shift from road to rail.
(iii) Suggestions related to marketing strategy /pricing etc.
(iv) Suggestion on Wagons & Locos.
(v) Any other enablers needed (administrative, Delegation of Power)
3. The above information/inputs and views must be communicated urgently to the

undersigned latest by 6५ of May, 2022. Further deliberations if required will be carried
out by VC.

With regards, LL

Wwe
(R.N. Singh)

Sh. Arun Kumar Jain
Additional General Manager
South Central Railway
Secunderabad